Table 4 Quantities of survey price for alternative No. 1

From: Integrated framework for existing building alternatives by the building information modeling

Routine work

No

Item

Cost $

Cost/Unit

Quantity

1

By flat meter: Breaking mosaic tiles and transporting waste to public landfills

3314

2.46

1346.07

2

By linear meter: crushing the entrance stairs Marble with the transfer of waste to public landfills

31

2.46

12.42

3

By linear meter: crushing the Marble external stairs. including (existing and sleeping) with transporting waste to public landfills

12

2.46

4.96

4

By flat meter: crushing the entrance stairs Marble with the transfer of waste to public landfills

148

2.46

60.07

5

By the flat meter: crushing the clay brick walls and transporting the waste to public landfills

1484

2.19

678.42

6

By the cubic meter: crushing the clay brick walls and transporting the waste to public landfills

246

15.32

16.035

7

By the flat meter: crushing the cement brick walls and transporting the waste to public landfills

838

2.19

383.1

8

By the cubic meter: crushing the cement brick walls and transporting the waste to public landfills

15.32

0

9

By the flat meter: crushing the Ceramic tiles brick floor and transporting the waste to public landfills

163

1.64

99.58

10

By the flat meter: crushing the Ceramic tiles brick walls and transporting the waste to public landfills

776

1.64

472.73

11

By flat meter: Supplying and installation of 12 cm thick clay brick walls

2671

8.48

315

12

By cubic meter: Supplying and installation of 25 cm thick clay brick walls

9530

72.21

131.98

13

By flat meter: Supplying and installation of 12 cm thick cement brick walls

2315

9.03

256.52

14

By cubic meter: Supplying and installation of 25 cm thick cement brick walls

1472

72.21

20.39

15

By flat meter: Supplying and installation of tempered glass walls

768

32.82

23.39

16

By number: Supplying and installation of aluminum window for bathrooms, size 1.10 × 0.9 m

131

65.64

2

17

By number: Supplying and installation of aluminum window with two sliding folds for bathrooms, size 1.10 × 0.9 m

656

65.64

10

18

By number: Supplying and installation of accordion door for bathrooms, size 2.10  × 0.9 m

246

16.41

15

19

By number: Supplying and installation of administration office door, size 2.10 × 1.80 m

3692

246.16

15

20

By number: Painting and installing and disassembling an interior office door with lacquer paint, size 2.10 × 0.9 m

1280

35.56

36

21

By number: Painting and installing and disassembling an bathroom door with lacquer paint, size 2.10 × 0.9 m

924

35.56

26

22

By number: Supplying and installation of an tempered glass door with two sliding folds, size 2.10 × 1.8 m

574

191.46

3

23

By flat meters: supplying and roughening the interior walls

10,056

3.83

2626.12

24

By flat meters: Supplying and making plastic paints for interior walls and ceilings

29,292

7.11

4119.12

25

By flat meters: Supplying and installation of ceramic floors (60 × 60 cm)

39,213

24.62

1593

26

By flat meters: Supplying and installation of porcelain walls (40 × 40 cm)

3765

8.75

430.13

27

By flat meters: Supplying and installation of porcelain walls (25 × 35 cm)

6186

12.31

502.645

28

By flat meter: supplying and making an insulating layer for surfaces exposed to moisture, with a thickness of 4 mm

3765

8.75

430.13

29

By flat meters: supplying and making a layer of concrete to protect the insulation of bathrooms

4706

10.94

430.13

30

By flat meters: Supplying and installation of a white wash basin size 0.4 × 0.5 m

1015

144.96

7

31

By flat meters: Supplying and installation of a white toilet size 0.4 × 0.65 m

2929

172.31

17

32

By linear meter: Supplying and instillation of 1 in. diameter PP feeding pipes

505

12.58

40.1

33

By linear meter: Supplying and installation of 3/4 in. diameter PP feeding pipes

335

9.57

35

34

By linear meter: Supplying and installation of 1 in. diameter UPVC drain pipes

368

8.75

42

35

By linear meter: Supplying and installation of 3 in. diameter UPVC drain pipes

368

17.50

21

36

By linear meter: Supplying and installation of 3 in. diameter UPVC column drain pipes

881

18.60

47.35

37

By linear meter: Supplying and installation of 1.5 in. diameter UPVC drainage ventilation shafts

61

8.75

7

38

By number: Supply and installation of a 1 in. diameter stopcock

394

21.88

18

39

By number: Supply and installation of a 3/4 in. diameter stopcock

794

18.05

44

40

By lump Sum: Maintenance and scavenging of aluminum works—windows

821

820.52

1

41

By flat meters: Supply and installation of Trista marble for the entrance and corridors

6981

31.73

220.02

42

By lump Sum: Polished marble for staircases and entrances

821

820.52

1

43

By lump Sum: Facade repaint

2735

2735.08

1

44

By lump Sum: Coordination of the landscape works and the price includes all raw materials, crushing and transporting waste to public landfills

3556

3555.60

1

 

Total

 

$150,816

 

Electric work

No

Item

Cost

Cost/unit

Quantity

1

By lump Sum: Supplying and installation of electrical works, and the price includes crushing and making of sand and transporting waste to public landfills (75% of the cost of routine works)

113,112

113,112

1

 

Total

$113,112

  

Quantity of survey

Routine work

$150,816

Electric work

$113,112

Total

$263,927