From: Integrated framework for existing building alternatives by the building information modeling
Demolition work | ||||
---|---|---|---|---|
No | Item | Costs | Cost/Unit | Quantity |
1 | By cubic meter: crushing reinforced concrete and the price includes transporting waste to public landfills | 29,798 | 11.87 | 2510.40 |
2 | By cubic meter: crushing plain concrete and the price includes transporting waste to public landfills | 810 | 1.50 | 540.00 |
3 | By flat meter: Breaking mosaic tiles and transporting waste to public landfills | 3050 | 1.30 | 2346.07 |
4 | By linear meter: crushing the entrance stairs Marble with the transfer of waste to public landfills | 23 | 1.25 | 18.63 |
5 | By linear meter: crushing the Marble external stairs, including (existing and sleeping) with transporting waste to public landfills | 558 | 1.25 | 446.4 |
6 | By flat meter: crushing the entrance stairs Marble with the transfer of waste to public landfills | 113 | 1.25 | 90.105 |
7 | By the flat meter: crushing the clay brick walls and transporting the waste to public landfills | 569 | 1.25 | 455.075 |
8 | By the cubic meter: crushing the clay brick walls and transporting the waste to public landfills | 605 | 1.50 | 403.2 |
9 | By the flat meter: crushing the cement brick walls and transporting the waste to public landfills | 194 | 1.50 | 129.525 |
10 | By the cubic meter: crushing the cement brick walls and transporting the waste to public landfills | 50 | 1.00 | 50 |
11 | By the flat meter: crushing the Ceramic tiles brick floor and transporting the waste to public landfills | 100 | 1.00 | 99.58 |
12 | By the flat meter: crushing the Ceramic tiles brick walls and transporting the waste to public landfills | 473 | 1.00 | 472.73 |
13 | By lamp sum: crushing electrical works and the price includes transporting waste to public landfills | 29,074 | 29,074 | 1 |
Total | $65,416 |
Quantity of survey | |
---|---|
Total | $65,416 |